Completion of another major rail project
Friday, 29 January 2010
A landmark project has been completed today with the final
sleepers being laid on a $105 million upgrade of the rail link
between Melbourne and the South Australian border.
The final stage of the project saw the upgrade of the dual gauge
track between Melbourne and Geelong with new track and concrete
sleepers. This $6 million stage involved laying 26,500 sleepers over
eight kilometres of track between Tottenham and Newport, and 10
kilometres of track between Gheringhap and North Geelong.
The overall project involved laying 401,000 standard gauge
sleepers between Maroona and Serviceton, approximately 270
kilometres in length, and 22,750 dual gauge sleepers in the
Melbourne metro and Geelong areas, approximately 18 kilometres in
length.
In addition to these works there have been bridge strengthening
works and new turnouts, as well as the upgrading of 80 level
crossings.
The project was undertaken as part of a $1.2 billion equity
injection into the Australian Rail Track Corporation by the
Australian Government.