The Nation Building – Economic Stimulus Plan (the Plan), a key component of the Australian Government’s stimulus strategy, provided around $27 billion towards more than 48,000 short and medium term building and construction projects. The charts below provide an overview of achievements to 30 June 2011.

Nation Building - Economic Stimulus Plan overview

Graph showing percentage of approved, underway and completed Economic Stimulus Plan projects
  • 48,681 (100%) projects approved
  • 48,669 (100%) projects underway
  • 43,565 (89%) projects completed

As at 30 June 2011

Education

Graph showing percentage of approved, underway and completed Education projects
  • 24,343 (100%) projects approved
  • 24,334 (100%) projects underway
  • 23,118 (95%) projects completed

As at 30 June 2011

More information on Education projects can be found on the Education page.

Community Infrastructure

Graph showing percentage of approved, underway and completed Community Infrastructure projects
  • 3,350 (100%) projects approved
  • 3,348 (99.7%) projects underway
  • 3,281 (97.9%) projects completed

As at 30 June 2011

More information on Community Infrastructure projects can be found on the Community Infrastructure page.

Road and Rail

Graph showing percentage of approved, underway and completed Road and Rail projects
  • 923 (100%) projects approved
  • 922 (99.9%) projects underway
  • 898 (97.3%) projects completed

As at 30 June 2011

More information on Road and Rail projects can be found on the Road and Rail page.

Social Housing

Graph showing percentage of approved, underway and completed Social Housing projects
  • 19,236 (100%) projects approved
  • 19,236 (100%) projects underway
  • 15,439 (80%) projects completed

As at 30 June 2011

More information on Social Housing projects can be found on the Social Housing page.

Defence Housing

Graph showing percentage of approved, underway and completed Defence Housing Projects
  • 829 (100%) projects approved
  • 829 (100%) projects underway
  • 829 (100%) projects completed

As at 30 June 2011

More information on Defence Housing projects can be found on the Defence Housing page.

Information on the Renewable Energy Bonus Scheme can be found on the Renewable Energy Bonus Scheme page.

Information on the Bonus Payments can be found on the Bonus Payments page.